Checklist Library

Checklist – Vessel Dry Dock

Safety, Decommissioning, Inspection, Repair, Reboot

Planning

1.1 AFE project configuration?

1.2. Work order created?

1.3. HES representative notified?

1.4. Notified Marine Chemist?

1.5. Reported operations?

1.6. Logistics/ Central Dispatch Notified?

Safety

2.1 Secondary means of egress?

2.2. MSD download verified?

2.3. Diverted MSD discharge?

2.4. Greywater discharge(s) diverted?

2.5. Chiller water discharge diverted?

2.6. Sufficient ground power?

Work Permits/ Lockout Tagout

3.1.HES representative on site?

3.2. Marine Chemist Certificate Obtained?

3.3. Secure work permit issued?

3.4. Verified, isolated, locked out and tagged energy sources?

Port propulsion

Rudder system

5.1 Port rudder

5.2 Starboard rudder

5.3 Port outboard flanking rudder

5.4 Port inner flanking rudder

5.5 Outboard starboard flanking rudder

5.6 Starboard inner flank rudder

5.7 steering jockey bars

5.8 Steering pins/bushes

5.9 Hydraulic Steering Cylinders/Hoses

5.10 address link

5.11 Steering pump system (tank, pump, motor, coupling)

5.12 electronic steering system

5.13 Flanking Jockey Bars

5.14 Flanking Pins/Bushings

5.15 Lateral Hydraulic Rams/Hoses

5.16 flanking link

5.17 Side pump system (tank, pump, motor, coupling)

5.18 Electronic flanking system

Peel

6.1 overall condition

6.2 hull lining

6.3 mudguard

6.4 Harbor Trailer Knee

6.5 Starboard towing knee

6.6 Port Grid/Skin Coolers

6.7 Starboard grate/skin coolers

6.8 Sea Chest

6.9 Were living organisms removed?

Re-commissioning

General

8.1 Comments?

8.2 Future projects?

8.3 Equipment to be rebuilt as a spare?

FINISH CHECKLIST

Comments

 

Name and Signature